This page provides step-by-step instructions on how to enter and edit Subpart H Cement Production kiln information for kilns that are monitored by CEMS.

Step 1: Add a kiln

To add a kiln that is monitored by CEMS, find the CEMENT KILN SUMMARY (Cement Kilns Monitored by CEMS) table on the Subpart Overview page and click the link titled "ADD a Cement Kiln Monitored by CEMS."

To edit identification information for a kiln, click the edit icon or the Name/ID link located in the first column of the table.

To delete a kiln, click the delete icon or the red “X” icon located in the last column of the table.


Subpart H: Step 1 - Add a Klin

Step 2: Indicate CEMS utilization for a kiln

For each kiln that is monitored by CEMS at your facility, confirm whether or not the kiln utilizes CEMS.

Note that when adding a new kiln you are prompted to answer the CEMS question immediately (the answer to this question will default to “No” for kiln added using the “ADD a Cement Kiln” link and will default to “Yes” for units added using the “ADD a Cement Kiln Monitored by CEMS” link).

The CEMS response may be changed here and the kiln information will be relocated to the appropriate table on the Subpart Overview page.

Subpart H: Step 2 - Indicate CEMS Utilization

 

When finished, click SAVE to save your data, then click BACK TO OVERVIEW to return to the Subpart Overview page.

Step 3: Enter required information for a kiln

For each kiln that is monitored by CEMS at your facility, Subpart H requires you to report a unique identifier and optional description

Subpart H: Step 3 - Enter Required Information

 

When finished, click SAVE to save your data then click BACK TO OVERVIEW to return to the Subpart Overview page.

Step 4: Enter additional required monthly information for a kiln

To enter additional required information for a kiln that is monitored by a CEMS, locate the kiln in the CEMENT KILN SUMMARY (Cement kilns monitored by CEMS) table on the Subpart Overview page and click OPEN.

Subpart H: Step 4 - Enter Required Monthly Information

For each month and for each kiln, enter the following required information:

  • An indication if a missing data procedure was used to determine the monthly clinker production
  • Clinker production in short tons
Subpart H: Step 4 - Click the FINISHED button after reviewing

 

When finished, click FINISHED.

Step 5: Repeat Steps 1-4

Repeat Steps 1-4 until all kilns that are monitored by CEMS have been added for your facility, then proceed to Subpart H Emissions Information for Kilns Monitored by CEMS for RY2014 and Later Years.

See Also

Screen Errors

Using e-GGRT to Prepare Your Subpart H Report for RY2014 and Later Years

Subpart Validation Report